Checklists for Hotel Project Stakeholders

To ensure successful delivery of your hotel project, we have made checklists for key stakeholders.

OD stands for Open Date or the date the hotel should be ready for customers. Schedule is given relative to open date, for example OD - 3 Months is to be read as “3 months before open date”.

If you are going through the document and realize an item is delayed from the reference schedule, contact your Mount Kelvin delivery engineer immediately.

Operator

OK What Schedule Why
  Contract signed with Mount Kelvin OD -3 Months Custom components like printed switches have long lead times
  Interior designer contacts to Mount Kelvin OD -3 Months First decision should be switch prints and colors
  Electrical Designer contacts to Mount Kelvin OD -3 Months For coordination in electrical design phase
  Network contractr contacts to Mount Kelvin OD -3 Months Contacts for both cabling and active network devices are needed to make sure network is ready for commissioning
  Room scene concepts and schedules set OD -1 Month These may be changed after too, but to start commissioning some initial configuration needs to be agreed upon

Interior Designer

OK What Schedule Why
  Switch colors and prints decided OD -3 Months Custom components like printed switches have long lead times
  Luminaire type lists delivered to Mount Kelvin OD -2 Months Luminaire types need to be known to select control components
  Luminaires are ordered without integrated switches OD -2 Months In Mount Kelvin rooms, luminaires are controlled via wireless switches. An integrated switch in addition will create a confusing user experience.
  Choices for other electrical components made OD -2 Months Power sockets, especially power sockets installed in the same frame as switches should visually match
  Components for special rooms are chosen OD -2 Months High accessibility rooms, for example, have additional component needs. Ensure that these components match the visual style and electrical contractor won’t be responsible for designing them.
  Suggest a suitable location for the motion sensors OD -2 Months One motion sensor needs to be placed near the center of each room. Where should it be placed in practice?

Electrical Designer

OK What Schedule Why
  Correct drivers selected for each luminaire OD -3 Months Driver lead times are usually short, but large volumes may cause issues
  Each floor has a suitable number of gateway locations OD -3 Months Multiple gateways ensure smooth network operation
  Each gateway location has both a power socket and ethernet connectivity OD -3 Months Gateway needs power and a functional internet connection
  Network contractor is informed about switch / router needs OD -3 Months Cabling is not enough for gateways, the network contractor needs to provide switches, firewalls and an internet connection

Electrical Contractor

OK What Schedule Why
  Luminaire orders placed OD -3 Months Lead time may be longer than usual due to need for specific driver & no integrated switches
  Driver orders placed OD -2 Months For many luminaires, a separate driver unit is used
  Orders for power sockets and other installation accessories placed OD -2 Months Ensure correct colors especially for USB power sockets
For each room
  All luminaires in all rooms are installed OD -1 Months  
  All switches in all rooms are installed OD -1 Months  
  All motion sensor in all rooms are installed OD -1 Months  
  Each entrance door for each room has a door sensor OD -1 Months  
  Door sensor blinks when door is opened or closed OD -1 Months  
  All luminaires in all rooms light up when powered OD -1 Months Commissioning cannot begin before all devices get power

Network Contractor

OK What Schedule Why
  Network requirements are clear OD - 3 Months To ensure correct delivery of network
  Active network elements installed OD - 1 Months  
  Patch cabling installed in distribution cabinets OD - 1 Months  
  Patch cabling installed in gateway installation locations OD - 1 Months  
  Firewall ports open OD - 1 Months In accordance with Networking Requirements